Hooksett Road from East Dunbarton Road to the Town line will be reclaimed and paved this year. All work will be completed by the Department of Public Works and our subcontractors.
Due to the narrow width of the road, DPW suggests finding and alternate route until work is completed. Significant delays should be expected between 7AM - 5PM. Please see traffic alert here. Residents within the work zone will be allowed in and out as needed but should also expect delays.
9/8/15 DPW crews will mobilize and star drainage work on street. Tree work will also be occuring.
9/15/15 - Tree work was completed last week and this week DPW crews are removing stumps along the edges of the road. All drianage work has been completed on the road. Waiting to schedule reclaim and paving with our subcontractor.
9/22/15 - Road will be reclaimed tomorrow and left gravel until next week. Paving will be scheduled for next week.
9/28/15 - Road was reclaimed last week and rough graded by DPW. Paving scheduled this week.
10/1/15 - Hooksett Road survived the weather, was fine graded today and will be paved tomorrow. Please expect delays and find an alternate route. Thank you!
10/5/15 - Busy day last Friday - Road was paved, structures were raised and curbing installed. Final cleanup work will occur this week and next including blending in of all driveways, loaming, seeeding, adjusting mailboxes and installation of riprap as needed to control drainage off the road.
![]() |
![]() |
![]() |
![]() |
10/20/15 - Guardrail was installed last week and there is still some final cleanup and misc punchlist items to take care of on this site. Our crews have been over at Black Brook Road trying to get that ready for reclaim and paving but they will be back here soon to tie up loose ends. We thank you for your patience.
10/28/15 - Crews were out on site recently replacing a driveway culvert, backing up curbing, loaming and installing new mailbox posts.
12/4/15 - Work has been completed on this site and DPW crews will return in the spring to complete any punchlist items that are needed. Thank you for your patience during construction and please call with any questions or concerns.
If you could take a moment and fill out our short post-construction survey, we would be most appreciative of the feedback:
http://www.goffstown.com/dpwsurvey.html