The budgeted 2022 Road Plan addresses 146,000 square yards of pavement - over 8.5% of the entire Goffstown road network. The planned work includes three distinct categories of work:
- Reclaim projects - grinding up old pavement, drainage installation, and new 2.5" base pavement
- Overlay projects - includes both 1.5" topcoats of streets reclaimed in the previous year, plus regular (around 10 year) overlays to keep our "good roads good"
- Shim/overlay projects to restore the riding surface of roads that have failed, but cannot be fully rebuilt due to cost and schedule constraints